Skip to main content
Maepole Cumming
26-027ESTIMATE + MARKUP

Maepole Cumming

Ecker ConstructionCastleberry & Bethelview Road, Cumming, GA 30040
Subtotal
$131,069.00
Markup
$42,597.43
32.5% of cost
Sell Price
$173,666.43
Gross Margin
24.5%
Status
Within Limits

Extracted Line Items

100% accuracy
DescriptionTradeQtyUnitUnit PriceBase CostMarkupSell Price
3000psi 24" C&G (LF)
26-027 Maepole Cumming Proposal.pdf(Proposal → Line 1)
Curb & Gutter709LF$22.00$15,598.00$5,069.35$20,667.35
Stamped & Colored Concrete (SF)
26-027 Maepole Cumming Proposal.pdf(Proposal → Line 2)
Concrete232SF$17.00$3,944.00$1,281.80$5,225.80
8" Dumpster Pad (SF)
26-027 Maepole Cumming Proposal.pdf(Proposal → Line 3)
Concrete370SF$12.00$4,440.00$1,443.00$5,883.00
6" Concrete Paving (SF)
26-027 Maepole Cumming Proposal.pdf(Proposal → Line 4)
Concrete3,650SF$8.00$29,200.00$9,490.00$38,690.00
Curb Inlets (EA)
26-027 Maepole Cumming Proposal.pdf(Proposal → Line 5)
Drainage4EA$175.00$700.00$227.50$927.50
3000psi 4" Sidewalk (SF)
26-027 Maepole Cumming Proposal.pdf(Proposal → Line 6)
Flatwork1,711SF$7.00$11,977.00$3,892.53$15,869.53
ADA Ramp (EA)
26-027 Maepole Cumming Proposal.pdf(Proposal → Line 7)
Flatwork2EA$750.00$1,500.00$487.50$1,987.50
Building Concrete (LS)
26-027 Maepole Cumming Proposal.pdf(Proposal → Line 8)
Concrete1LS$63,710.00$63,710.00$20,705.75$84,415.75
Totals$131,069.00$42,597.43$173,666.43

Trade Breakdown

TradeBase CostMarkup %Markup $Sell PriceGross Margin
Concrete
$101,294.0032.5%$32,920.55$134,214.5524.5%
Curb & Gutter
$15,598.0032.5%$5,069.35$20,667.3524.5%
Flatwork
$13,477.0032.5%$4,380.03$17,857.0324.5%
Drainage
$700.0032.5%$227.50$927.5024.5%
Project Total$131,069.0032.5%$42,597.43$173,666.4324.5%

Cost vs. Proposal AnalysisFROM BAM COST SHEET

Line ItemActual CostProposal PriceProfitMarkup %Margin
3000psi 24" C&G (LF)
Cost from: 26-027 Maepole Cumming Proposal.xlsx (Profit Sheet → Row 1)
$11,344.00$15,598.00$4,254.0037.5%27.3%
Stamped & Colored Concrete (SF)
Cost from: 26-027 Maepole Cumming Proposal.xlsx (Profit Sheet → Row 2)
$2,320.00$3,944.00$1,624.0070.0%41.2%
8" Dumpster Pad (SF)
Cost from: 26-027 Maepole Cumming Proposal.xlsx (Profit Sheet → Row 3)
$4,540.00$4,440.00$-100.00-2.2%-2.3%
6" Concrete Paving (SF)
Cost from: 26-027 Maepole Cumming Proposal.xlsx (Profit Sheet → Row 4)
$20,075.00$29,200.00$9,125.0045.5%31.3%
Curb Inlets (EA)
Cost from: 26-027 Maepole Cumming Proposal.xlsx (Profit Sheet → Row 5)
$500.00$700.00$200.0040.0%28.6%
3000psi 4" Sidewalk (SF)
Cost from: 26-027 Maepole Cumming Proposal.xlsx (Profit Sheet → Row 6)
$7,272.00$11,977.00$4,705.0064.7%39.3%
ADA Ramp (EA)
Cost from: 26-027 Maepole Cumming Proposal.xlsx (Profit Sheet → Row 7)
$600.00$1,500.00$900.00150.0%60.0%
Building Concrete (LS)
Cost from: 26-027 Maepole Cumming Proposal.xlsx (Profit Sheet → Row 8)
$55,400.00$63,710.00$8,310.0015.0%13.0%
Totals$102,051.00$131,069.00$29,018.0028.4%22.1%

Cost data sourced from Lutum Co.'s internal BAM sub-cost tracking sheets. Actual costs reflect material + labor before overhead and G&A.

See this with your own documents

Upload your proposals, takeoffs, and pay apps. BuildBid extracts the data, applies your markup rules, and gives you a sell price in seconds.

Real project data from Lutum Co. archives. Processed through BuildBid's extraction and markup engine.
BuildBid — AI Construction Estimating Software for Review-First Teams