26-012ESTIMATE + MARKUP

FKC Adairesville

Ecker Construction909 Curtis Parkway SE, Calhoun, GA
Subtotal
$142,843.00
Markup
$46,423.98
32.5% of cost
Sell Price
$189,266.98
Gross Margin
24.5%
Status
Within Limits

Extracted Line Items

100% accuracy
DescriptionTradeQtyUnitUnit PriceBase CostMarkupSell Price
3000psi 24" C&G (LF)
26-012 FKC.pdf(Proposal → Line 1)
Curb & Gutter1,390LF$22.00$30,580.00$9,938.50$40,518.50
Throats and Tops (EA)
26-012 FKC.pdf(Proposal → Line 2)
Structures3EA$2,000.00$6,000.00$1,950.00$7,950.00
3000psi 4" Sidewalk (SF)
26-012 FKC.pdf(Proposal → Line 3)
Flatwork1,935SF$7.00$13,545.00$4,402.13$17,947.13
ADA Ramp (EA)
26-012 FKC.pdf(Proposal → Line 4)
Flatwork3EA$750.00$2,250.00$731.25$2,981.25
Bollards (EA)
26-012 FKC.pdf(Proposal → Line 5)
Concrete8EA$350.00$2,800.00$910.00$3,710.00
4000psi 8" Generator Pad (SF)
26-012 FKC.pdf(Proposal → Line 6)
Concrete225SF$12.00$2,700.00$877.50$3,577.50
4000psi 8" Dumpster Pad (SF)
26-012 FKC.pdf(Proposal → Line 7)
Concrete414SF$12.00$4,968.00$1,614.60$6,582.60
Building Concrete (LS)
26-012 FKC.pdf(Proposal → Line 8)
Concrete1LS$80,000.00$80,000.00$26,000.00$106,000.00
Totals$142,843.00$46,423.98$189,266.98

Trade Breakdown

TradeBase CostMarkup %Markup $Sell PriceGross Margin
Concrete
$90,468.0032.5%$29,402.10$119,870.1024.5%
Curb & Gutter
$30,580.0032.5%$9,938.50$40,518.5024.5%
Flatwork
$15,795.0032.5%$5,133.38$20,928.3824.5%
Structures
$6,000.0032.5%$1,950.00$7,950.0024.5%
Project Total$142,843.0032.5%$46,423.98$189,266.9824.5%

Cost vs. Proposal AnalysisFROM BAM COST SHEET

Line ItemActual CostProposal PriceProfitMarkup %Margin
3000psi 24" C&G (LF)
Cost from: 26-012 FKC_AWARDED.xlsx (Profit Sheet → Row 1)
$20,761.00$30,580.00$9,819.0047.3%32.1%
Throats and Tops (EA)
Cost from: 26-012 FKC_AWARDED.xlsx (Profit Sheet → Row 2)
$3,900.00$6,000.00$2,100.0053.8%35.0%
3000psi 4" Sidewalk (SF)
Cost from: 26-012 FKC_AWARDED.xlsx (Profit Sheet → Row 3)
$7,450.00$13,545.00$6,095.0081.8%45.0%
ADA Ramp (EA)
Cost from: 26-012 FKC_AWARDED.xlsx (Profit Sheet → Row 4)
$1,350.00$2,250.00$900.0066.7%40.0%
Bollards (EA)
Cost from: 26-012 FKC_AWARDED.xlsx (Profit Sheet → Row 5)
$1,200.00$2,800.00$1,600.00133.3%57.1%
4000psi 8" Generator Pad (SF)
Cost from: 26-012 FKC_AWARDED.xlsx (Profit Sheet → Row 6)
$1,800.00$2,700.00$900.0050.0%33.3%
4000psi 8" Dumpster Pad (SF)
Cost from: 26-012 FKC_AWARDED.xlsx (Profit Sheet → Row 7)
$2,898.00$4,968.00$2,070.0071.4%41.7%
Building Concrete (LS)
Cost from: 26-012 FKC_AWARDED.xlsx (Profit Sheet → Row 8)
$71,345.00$80,000.00$8,655.0012.1%10.8%
Totals$110,704.00$142,843.00$32,139.0029.0%22.5%

Cost data sourced from Lutum Co.'s internal BAM sub-cost tracking sheets. Actual costs reflect material + labor before overhead and G&A.

See this with your own documents

Upload your proposals, takeoffs, and pay apps. BuildBid extracts the data, applies your markup rules, and gives you a sell price in seconds.

Real project data from Lutum Co. archives. Processed through BuildBid's extraction and markup engine.
BuildBid — AI Construction Estimating Software for Review-First Teams