Skip to main content
Auburn Square
25-101ESTIMATE + MARKUP

Auburn Square

Gorman Construction2800 M.L.K. Jr Dr SW, Atlanta, GA 30311
Subtotal
$313,765.00
Markup
$101,973.63
32.5% of cost
Sell Price
$415,738.63
Gross Margin
24.5%
Status
Within Limits

Extracted Line Items

100% accuracy
DescriptionTradeQtyUnitUnit PriceBase CostMarkupSell Price
3000psi 24" C&G (LF)
25-101 Auburn Square Proposal.pdf(Proposal → Line 1)
Curb & Gutter4,540LF$20.25$91,935.00$29,878.88$121,813.88
DOT 30" C&G (LF)
25-101 Auburn Square Proposal.pdf(Proposal → Line 2)
Curb & Gutter285LF$28.00$7,980.00$2,593.50$10,573.50
Throats and Tops (EA)
25-101 Auburn Square Proposal.pdf(Proposal → Line 3)
Structures1EA$2,000.00$2,000.00$650.00$2,650.00
Curb Inlets (EA)
25-101 Auburn Square Proposal.pdf(Proposal → Line 4)
Drainage2EA$175.00$350.00$113.75$463.75
3000psi 4" Sidewalk (SF)
25-101 Auburn Square Proposal.pdf(Proposal → Line 5)
Flatwork31,320SF$6.25$195,750.00$63,618.75$259,368.75
ADA Ramp (EA)
25-101 Auburn Square Proposal.pdf(Proposal → Line 6)
Flatwork21EA$750.00$15,750.00$5,118.75$20,868.75
Totals$313,765.00$101,973.63$415,738.63

Trade Breakdown

TradeBase CostMarkup %Markup $Sell PriceGross Margin
Flatwork
$211,500.0032.5%$68,737.50$280,237.5024.5%
Curb & Gutter
$99,915.0032.5%$32,472.38$132,387.3824.5%
Structures
$2,000.0032.5%$650.00$2,650.0024.5%
Drainage
$350.0032.5%$113.75$463.7524.5%
Project Total$313,765.0032.5%$101,973.63$415,738.6324.5%

Cost vs. Proposal AnalysisFROM BAM COST SHEET

Line ItemActual CostProposal PriceProfitMarkup %Margin
3000psi 24" C&G (LF)
Cost from: 25-101 Auburn Square Proposal_AWARDED.xlsx (Profit Sheet → Row 1)
$72,640.00$91,935.00$19,295.0026.6%21.0%
DOT 30" C&G (LF)
Cost from: 25-101 Auburn Square Proposal_AWARDED.xlsx (Profit Sheet → Row 2)
$7,125.00$7,980.00$855.0012.0%10.7%
Throats and Tops (EA)
Cost from: 25-101 Auburn Square Proposal_AWARDED.xlsx (Profit Sheet → Row 3)
$1,300.00$2,000.00$700.0053.8%35.0%
Curb Inlets (EA)
Cost from: 25-101 Auburn Square Proposal_AWARDED.xlsx (Profit Sheet → Row 4)
$150.00$350.00$200.00133.3%57.1%
3000psi 4" Sidewalk (SF)
Cost from: 25-101 Auburn Square Proposal_AWARDED.xlsx (Profit Sheet → Row 5)
$133,110.00$195,750.00$62,640.0047.1%32.0%
ADA Ramp (EA)
Cost from: 25-101 Auburn Square Proposal_AWARDED.xlsx (Profit Sheet → Row 6)
$7,350.00$15,750.00$8,400.00114.3%53.3%
Totals$221,675.00$313,765.00$92,090.0041.5%29.3%

Cost data sourced from Lutum Co.'s internal BAM sub-cost tracking sheets. Actual costs reflect material + labor before overhead and G&A.

See this with your own documents

Upload your proposals, takeoffs, and pay apps. BuildBid extracts the data, applies your markup rules, and gives you a sell price in seconds.

Real project data from Lutum Co. archives. Processed through BuildBid's extraction and markup engine.
BuildBid — AI Construction Estimating Software for Review-First Teams